HVAC · Chilled water · Precision cooling
Cooling sized from measured load, not floor area.
Air Cooling designs, installs and maintains comfort, process and critical-room cooling. Every system starts with a survey and ends with commissioning data you can audit.
- Design basis
- Measured heat-load survey, CIBSE methodology
- Refrigerant compliance
- F-gas Regulation documented on every install
- Critical response
- 4-hour target on contracted critical faults
- Handover
- As-builts, test certificates and O&M manual
Services
Four disciplines, one accountable team.
Design, installation, maintenance and controls are delivered by the same engineers, so faults and decisions don't get lost between contractors.
- 01
HVAC design and installation
Load calculation, system selection, and commissioned installation.
- HVAC design
- HVAC installation
- heat load calculation
- 02
Planned preventive maintenance
Scheduled service contracts that cut breakdowns and energy use.
- preventive maintenance
- HVAC service contract
- planned maintenance
- 03
Data centre and server room cooling
Precision cooling with N+1 resilience and monitored setpoints.
- data centre cooling
- server room cooling
- precision cooling
- 04
Chilled water and plant rooms
Chillers, pumps and controls for process and commercial buildings.
- chilled water
- chiller plant
- plant room
How we work
Every project follows the same four steps.
The steps are fixed so you can see where a project is and what evidence exists at each point.
- 01
Survey
We measure the building or room as it is: envelope, gains, occupancy and existing plant.
- 02
Model
Peak and part-load calculations, with every assumption written down for review.
- 03
Specify
Equipment schedule, layouts and performance targets your engineer can check.
- 04
Install & commission
Installed under permit, with recorded airflow, charge and setpoint results.
Projects
Recent work across sectors.
Commercial2025
Regional office VRF retrofit
A four-storey office with an ageing split system suffered uneven comfort across floors and rising running costs. The fabric could not take a full chilled-water conversion within the lease terms.
Read the project
Data centre2025
Tier III server hall cooling
A growing colocation hall had rack densities above its original design basis, with hot spots at the end of aisles and no redundancy on the precision cooling.
Read the project
Industrial2024
Plant room chiller upgrade
A manufacturing site ran two constant-speed chillers and a fixed-speed pump set, causing excess energy use and frequent short-cycling during part-load operation.
Read the project
Start with a survey, not a sales call.
Tell us about the building or room. We'll confirm what we need to measure and what a survey costs before anything else.